III. Loading of New Molecular Sieve (Key Procedure)
Base Laying: Place coconut mat at the bottom of the tower first → Lay 5cm activated alumina balls → Cover with stainless steel wire mesh (to prevent molecular sieve leakage).
Nitrogen Protection: Purge the tower with nitrogen of ≥95% purity to reduce oxygen content and minimize moisture absorption of molecular sieve.
Layered Loading and Compaction (Core Step)
Feed materials slowly and vertically through a funnel to avoid particle breakage caused by falling from height.
Compact with a vibrating rod or evenly knock the tower wall with a wooden hammer every 30cm of loading height; control the bulk density within 670–690g/L.
Stop loading when reaching 5cm below the lower edge of the upper flange to reserve expansion space.
Cover the top with stainless steel wire mesh and coconut mat, then install flow distribution plate and spring/cylinder pressing device to prevent displacement and pulverization during operation.
Loading Quantity Control: The error of single tower ≤±5%, the error between two towers ≤±2% to avoid gas flow bias.
Refilling Notes: Perform secondary refilling after the new molecular sieve operates for 1 month (to compensate settlement gaps); conduct inspection and refilling every 6–12 months in the later operation period.